US Route 460 Corridor Improvements


Route-460-image.jpg

Suffolk, VA, USA | Virginia DOT

2011-2012 | DBF | USD $1,400 million

 

Project Description

The project involves the construction of 55 miles of new four-lane green field divided toll road connecting Petersburg and Suffolk. Construction cost of $1,400 million. It was awarded in 2013 to a joint venture led by Cintra and construction began in 2014. Project was later suspended in 2015 due to pending environmental approvals from the U.S. Army Corps of Engineers.

Services

Proposal Management

  • Negotiation and Selection of Qualified Partners (D&C)

  • Design Contracts Negotiation and Execution

  • Proposal Management (RFQ & RFP)

  • Technical Writing

Design Management

  • Design Coordination & Leadership

  • Design Due Diligence and Compliance

  • Preparation of ATCs

  • Preparation and Supervision of BOQs

Project Information


RoadsManuel Serra